Weekly Road Construction Report

  • Thursday, April 24, 2014

Here is the weekly road construction report for Hamilton County:

I-75 from MM 13.9 to MM 25.3 expansion of Chattanooga SmartWay Intelligent Traffic System:  Work on this project continues.  There will be daytime shoulder closures and short term nighttime outside lane closures throughout the project area as the contractor performs work for future traffic cameras and dynamic message signs.  Estimated completion date is May. 

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  Weather permitting, the contractor may have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  On the evening of Friday the contractor will close the left lane of U.S. 27 North and South between the Olgiati Bridge and Manning Street, along with Manning Street itself, to pour the bridge deck for the bridge over Manning Street.  All work is weather permitting.  If this work is cancelled due to weather, it will be rescheduled to take place on the next available day.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February 2015.  

SR-58 resurfacing from Lakewood Acres Road (LM. 9.20) to Greenwood Road (LM 14.68):  Work on this project is scheduled to begin during this report period.  Milling and paving operations are limited to Sunday through Thursday nights between 7 p.m.-6 a.m.  There will be temporary lane closures as needed on this project.  At least one lane in each direction will remain open at all times.  Estimated completion date is July.  

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of clearing and taking care of environmental measures in order to start on road and drainage.  Traffic will not be impacted at this time therefore, no lane closures are needed.  Estimated project completion date is September.  


Happenings
Chattanooga Zoo Hosts Spirits In The Wild 21+ Event
  • 5/1/2024

The Chattanooga Zoo is once again hosting their signature 21+ event, Spirits in the Wild on May 18 from 6-9 p.m. The after-hours event features beers, wines and spirits from around the world, ... more

Did You Know? Tribe
Did You Know? Tribe
  • 5/1/2024

The recent surprise announcement that the only opposition to the current “Chief Conductor” on the proposed “Choo Choo Express” in the next mayoral race and future in our booming municipality ... more

Lily Hughes, Local 19-Year-Old Equestrian, To Compete In Mustang Champions Competitions
Lily Hughes, Local 19-Year-Old Equestrian, To Compete In Mustang Champions Competitions
  • 4/30/2024

Lily Hughes, a 19-year-old equestrian from Flat Top Mountain, will compete in two major Mustang Champions competitions this year: the Mustang Challenge in Las Vegas, Nv., and the Mustang Classic ... more