Weekly Road Construction Report

  • Thursday, June 22, 2017

Here is the weekly road construction report for Hamilton County:

U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:  Work on this project continues.  The speed limit on U.S. 27 in the construction zone is 45 MPH.  The contractor may have temporary lane or shoulder closures on U.S. 27 between 7 p.m.-6 a.m.  The new permanent Exit 1A from U.S. 27 North to Main Street / Carter Street/ Convention Center is now open.  The intersection of Carter Street and 13th Street is now a 4-way stop.  On Friday at 7 p.m. through Saturday at noon, there will be a temporary double right lane closure on U.S. 27 South from north of the Olgiati Bridge to the south end of the project to allow the contractor perform grinding, paving and striping for the next phase of the project.  Ramp traffic will be required to yield during this work.  At least one lane will remain open in each direction on U.S. 27.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is July 2019.  For more info, visit the project website http://www.tn.gov/tdot/topic/US27-reconstruction-chattanooga.  [Dement Construction Co., LLC/JM/CNP230] 

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  During this report period the contractor may have intermittent lane closures throughout the project from 9 a.m.-4 p.m.  Flaggers will assist with traffic control as needed.  Estimated project completion date is July. [Wright Brothers Const. Co. /Pruett/CNN279] 

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  During this report period, the contractor will have intermittent lane closures between 9 a.m.-2 p.m.  This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Hamlett Drive as the contractor installs road crossings and borings.  Traffic has been switched onto the newly-constructed section from the west end of the project to the Hurricane Creek Road/East Brainerd Road intersection, allowing the contractor to work on the other side of the roadway.  The contractor may have short-term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Original completion date is June 2017. Estimated project completion date is December. [Jones Brothers Contractors, LLC /Pruett/CNN383] 

SR-153/SR-319 (Hixson Pike) bridge repair on Hixson Pike over SR-153:  Work on this project continues.  Starting on Friday the contractor plans to open the outside lanes to traffic in both directions on the bridge on Hixson Pike over SR-153 and close the inside lanes in both directions at the same time.  This changeover may take several days depending on weather and any unknown factors.  This lane closure will be in place until late November 2017.  During this report period the contractor may have intermittent lane closures on SR-153 from 9 p.m.-6 a.m. to do work under the bridge.  If there are any temporary closures needed on SR-153 as part of this project, they will take place at nighttime on Sundays through Thursdays between 9 p.m.-6 a.m. and on weekdays on SR-153 South between 9 a.m.-3 p.m. and on SR-153 North between 7:30 a.m. and 3 p.m.  Flaggers will assist with traffic control as necessary during these temporary closures.  Estimated project completion date is May 2018. [Mid-State Construction Co. /Micka/CNQ941] 

U.S. 27 (SR-29) resurfacing from north of Signal Mountain Road (LM. 3.02) to north of SR-29 (MM. 6.0/LM 6.07):  Work on this project has begun.  The contractor will have temporary intermittent lane closures on Sundays through Thursdays between the hours of 8 p.m. each evening to 6 a.m. the following morning to mill and pave the roadway.  THP and flaggers will assist with traffic control as necessary during these temporary closures.  Estimated project completion date is June. [Wright Brothers Construction Co, Inc./Micka/CNQ189] 

The tunnel cleaning of the McCallie Tunnel on U.S. 11 (US 64, SR-2), the Stringers Ridge Tunnel on U.S. 127 (SR-8), and the Bachman Tubes on U.S. 41 (U.S. 76, SR-8):  The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes occurs normally on Wednesday and Thursday nights during the week with the 3rd Tuesday of the month.  Work hours are between 8 p.m.-6 a.m.  Tunnels will be closed during cleaning, and detours will be marked accordingly as each tunnel is cleaned.  Contract completion date is June.  [Diamond Specialized, Inc./Micka/CNQ174]


Happenings
East Ridge Hosts Craft Fair Benefiting East Ridge City Library
East Ridge Hosts Craft Fair Benefiting East Ridge City Library
  • 4/25/2024

The public is invited to join the “Friends of the East Ridge Library” as they host the first-ever Craft Fair to benefit East Ridge City Library this Saturday from 10 a.m.-5 p.m. at the library ... more

Diana Walters: A Boomer's Ruminations - What Successful Aging Means
Diana Walters: A Boomer's Ruminations - What Successful Aging Means
  • 4/24/2024

About 20 years ago, when I was in my mid-50s, I wrote a paper for my doctoral program, “What is Successful Aging?” After reading the essay, one professor, who was around 80, said I didn’t know ... more

Scenic City Clay Arts Partners With Association For Visual Arts For New Exhibit
  • 4/24/2024

Scenic City Clay Arts presents “Forces of Creativity,” an exclusive exhibition in partnership with the Association for Visual Arts, showcasing ceramic creations by veteran and military family ... more