Weekly Road Construction Report

  • Thursday, May 24, 2018

Here is the weekly road construction report for Hamilton County:

I-75 North Exit 1 interchange reconfiguration project at mile marker 1:   Work on this project continues. There is now only one exit ramp that allows drivers to turn both east and west on Ringgold Road at a signalized intersection. Traffic has been shifted onto the newly constructed portion of Camp Jordan Pkwy., and the intersection (I-75 NB off-ramp and SR-8/Camp Jordan Pkwy.) is now controlled by a traffic signal. Estimated project completion date is June.  [C.W. Matthews Contracting/City Of East Ridge/LCLPRGM] 

US-27 (I-124) widening from I-24/US-27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:   Work on this project continues. The contractor has closed the 12th Street tie-in ramp to US-27 South. This closure will be in place through June 18. Traffic from 12th Street will be detoured to Carter Street and then to westbound MLK Blvd. where motorists may access the US-27 South on-ramp. Detours are posted. Motorists should exercise caution when traveling through the construction zone and pay close attention to the detour signage posted. The speed limit on US-27 in the construction zone remains 45 MPH. On Tuesday the contractor will implement a temporary left lane closure for US-27 North, from I-24 to the Olgiati Bridge, from 7 p.m.-6 a.m., for setting the Phase 2 Beams at the 6th Street Bridge. During this time, 6th Street will be closed at the bridge, and traffic will be detoured using Gateway Ave / Martin Luther King Blvd / Pine Street. At the same time, the US-27 North off-ramp to 4th Street (Exit 1C) will be temporarily closed from 7-10 p.m., to remove barrier rail. Traffic will be detoured using MLK (Exit 1B) to Chestnut Street. Weather permitting, the contractor may implement temporary lane/shoulder closures on weeknights between the hours of 7 p.m.-6 a.m. At least one lane will remain open in each direction on US-27. THP will assist with traffic control on the project as necessary RESTRICTIONS: I-124 (US-27) Northbound Exit 1C 4th Street Off Ramp. No oversize/over-dimensional loads. Width Limit is 11 feet. Estimated project completion date is January 2020. [Dement Construction Company, LLC/Micka/CNP230]  

SR-111 resurfacing from SR-29 to Jones Gap Road:   During this report period the contractor will have lane closures in place during resurfacing operations. No closures will occur from 5-8 a.m. in the southbound direction and from 4-6 p.m. in the northbound direction. Flaggers will be on hand to assist as needed. Estimated project completion date is July. [Wright Brothers, LLC/Pruett/CNS020]  

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:   During this report period, the contractor will have intermittent lane closures between 9 a.m.-2 p.m. This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Bel-Air Road. Flaggers will assist with traffic control as needed.  Estimated project completion date is June. [Jones Bros. Contractors, LLC/Pruett/CNN383]  

The tunnel cleaning of the McCallie Tunnel on US-11 (US-64, SR-2), the Stringers Ridge Tunnel on US-127 (SR-8), and the Bachman Tubes on US-41 (US-76, SR-8):   The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes occurs between 8 p.m.-6 a.m. Tunnels will be closed during cleaning, and detours will be marked accordingly as each tunnel is cleaned. This work is scheduled to began on Wednesday at the McCallie tunnels (SR-2) and proceed to the Stringer's Ridge tunnel (SR-8) and on Thursday the Bachman Tubes (SR-8) will be cleaned.  Estimated project completion date is June. [ETI Environmental, Inc./Micka/CNR223]  

Utility Work on SR-58 northbound at LM 19.44 (500 ft. north of Sims Harris Road):   The contractor will implement a partial lane closure on weekdays from 9 a.m.-2 p.m. to install valve, vault and by-pass on existing water main. Utility construction signs, flagger signs, cones and flaggers will be present to assist with traffic control. Estimated project completion date is June. [UO-2007050968/Utility Permit/UTILITY] 


Happenings
Mason Keith Earns Eagle Scout Rank
Mason Keith Earns Eagle Scout Rank
  • 4/23/2024

Mason Keith, age 15, has earned the rank of Eagle Scout, the highest rank within the Boy Scouts of America program. He is a member of Troop 224, chartered to Elizabeth Lee Methodist Church in ... more

Children’s Nutrition Program Of Haiti Hosts Walk-A-Thon Mother’s Day Weekend
  • 4/23/2024

For more than 25 years, the Children’s Nutrition Program of Haiti – headquartered in Chattanooga – has been working in Haiti to raise a healthy generation of Haitian children, who can, in turn, ... more

Gallery At Blackwell Announces Summer Show And Opening Reception May 10
  • 4/23/2024

The Photographic Society of Chattanooga will hold a reception at the Gallery at Blackwell on Friday, May 10 from 6-8 p.m. to present the summer show. Refreshments will be provided and the public ... more