Here is the weekly road construction report for Hamilton County:
U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge: Work on this project continues. The speed limit on U.S. 27 in the construction zone is 45 MPH. The contractor may have temporary lane or shoulder closures on U.S. 27 between 7 p.m.-6 a.m. On Thursday night, between 7-10 p.m., there will be a temporary left lane closure on U.S. 27 North and South throughout the project limits for mowing. On Monday through Wednesday, the contractor will have a temporary left lane closure between 7 p.m.-6 a.m. on U.S. 27 North from the south end of the project to the bridge over 20th Street for paving the temporary ramp from I-24 East to U.S. 27 North. This is in preparation for an upcoming traffic shift on the northbound side of U.S. 27. Ramp traffic will not be affected during any of this work. The new traffic pattern is in place on U.S. 27 South. Traffic has been shifted to the right on U.S. 27 South from 4th Street to MLK Blvd. to allow the contractor to safely work in the middle portion of the road. Traffic is impacted by the loss of acceleration/merge areas onto U.S. 27 South from the on ramps at 4th Street and MLK Blvd. Ramp traffic must yield at these locations. At least one lane will remain open in each direction on U.S. 27. THP will assist with traffic control on the project as necessary. Estimated project completion date is July 2019. For more info, visit the project website http://www.tn.gov/tdot/topic/US27-reconstruction-chattanooga. [Dement Construction Co., LLC/JM/CNP230]
SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84): Work on this project continues. During this report period the contractor may have intermittent lane closures throughout the project from 9 a.m.-4 p.m. Flaggers will assist with traffic control as needed. Estimated project completion date is July. [Wright Brothers Const. Co. /Pruett/CNN279]
SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road: Work on this project continues. During this report period, the contractor will have intermittent lane closures between 9 a.m.-2 p.m. This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Hamlett Drive as the contractor installs road crossings and borings. Traffic has been switched onto the newly-constructed section from the west end of the project to the Hurricane Creek Road/East Brainerd Road intersection, allowing the contractor to work on the other side of the roadway. The contractor may have short-term lane closures to perform various operations on an as-needed basis. Flaggers will assist with traffic control as needed. Estimated project completion date is June 2018. [Jones Brothers Contractors, LLC /Pruett/CNN383]
SR-153/SR-319 (Hixson Pike) bridge repair on Hixson Pike over SR-153: Work on this project continues. The contractor will be working on the inside lanes of the bridge. The outside lanes in both directions are open to traffic. This lane closure will be in place until late November. During this report period the contractor may have intermittent lane closures on SR-153 from 9 p.m.-6 a.m. to do work under the bridge. If there are any temporary closures needed on SR-153 as part of this project, they will take place at nighttime on Sundays through Thursdays between 9 p.m.-6 a.m. and on weekdays on SR-153 South between 9 a.m.-3 p.m. and on SR-153 North between 7:30 a.m.-3 p.m. Flaggers will assist with traffic control as necessary during these temporary closures. Estimated project completion date is May 2018. [Mid-State Construction Co. /Micka/CNQ941]
U.S. 27 (SR-29) resurfacing from north of Signal Mountain Road (LM. 3.02) to north of SR-29 (MM. 6.0/LM 6.07): This project is complete. There are a few minor punch list items to be corrected. However, no lane closures will be required. Contractor has been authorized to remove all signs. Estimated project completion date is July. [Wright Brothers Construction Co, Inc./Micka/CNQ189]
HAMILTON COUNTY, SR-153 resurfacing from L.M. 7.11 (Chickamauga Dam) to LM 8.89 (Hixson Pike): Work on this project continues. Milling operation will require lane closures from 9:00 p.m. thru 6:00 a.m. Lane closures are limited to Sunday night thru Thursday night from 9:00 p.m. to 6:00 a.m. Estimated project completion date is September 2017. [Wright Brothers Construction Co, Inc./Micka/CNR133]
The tunnel cleaning of the McCallie Tunnel on U.S. 11 (US 64, SR-2), the Stringers Ridge Tunnel on U.S. 127 (SR-8), and the Bachman Tubes on U.S. 41 (U.S. 76, SR-8): The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes occurs between 8 p.m.-6 a.m. The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes will be done on Tuesday and Wednesday from 8 p.m.-6 a.m. Tunnels will be closed during cleaning, and detours will be marked accordingly as each tunnel is cleaned. Contract completion date is June 2018. [ETI Environmental, Inc./Micka/CNR223]