Weekly Road Construction Report

  • Thursday, December 8, 2016

Here is the weekly road construction report for Hamilton County: 

 U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:  Work on this project continues.  The speed limit on U.S. 27 in the construction zone has been lowered to 45 MPH.  The contractor may have temporary lane or shoulder closures on U.S. 27 between 7 p.m.-6 a.m.  TDOT contract crews have closed the on ramp from eastbound MLK Boulevard to U.S. 27 North until December.  A temporary left turn lane on eastbound MLK Boulevard has been constructed to allow traffic to access the alternate on-ramp to U.S. 27 North.  As the project progresses, there may be short term temporary lane closures for the safety of the traveling public on city streets within the project area.  Flaggers will assist with these closures and they will be properly signed in accordance with the Federal Highway Administration’s Manual on Uniform Traffic Control Devices. During Phase 1 of the U.S. 27 project, the contractor will be working on the northbound side of U.S. 27 on the bridges.  Work will consist of demolishing and reconstructing the outside sections of the bridges along U.S. 27 North.  Also on U.S. 27 South, they will be constructing a large retaining wall between the Olgiati Bridge and 6th Street.  At least one lane will remain open in each direction on U.S. 27.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is July 2019.  For more info, visit the project website http://www.tn.gov/tdot/topic/US27-reconstruction-chattanooga.  [Dement Construction Co., LLC/JM/CNP230] 

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  During this report period the contractor may have intermittent lane closures throughout the project from 9 a.m.-4 p.m. Flaggers will assist with traffic control as needed.  Estimated project completion date is May 2017. [Wright Brothers Const. Co. /Pruett/CNN279] 

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  Beginning on Saturday, the contractor will be shifting traffic at the intersection of Hurricane Creek Road and East Brainerd Road.  The shift will move East Brainerd Road eastbound through traffic (toward Fuller Road) into the eastbound left turn lane and close the eastbound through lane.  Westbound East Brainerd Road traffic (toward Graysville Road) will remain in its current alignment but will no longer have access to the westbound left turn lane.  The stop bar on Hurricane Creek Road will be moved back roughly 35’- 40' and no right turn on red will be permitted.  This will prevent northbound traffic on Hurricane Creek Road from interfering with eastbound East Brainerd Road traffic turning onto Hurricane Creek Road.  Traffic is scheduled to remain in this alignment until Monday, Dec. 19.  Also, during this report period, the contractor will have intermittent lane closures between 9 a.m.-2 p.m.  This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Hamlett Drive as the contractor installs road crossings and borings.  The contractor may have short-term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion is June 2017.  [Jones Brothers Contractors, LLC /Pruett/CNN383] 

The tunnel cleaning of the McCallie Tunnel on U.S. 11 (US 64, SR-2), the Stringers Ridge Tunnel on U.S. 127 (SR-8), and the Bachman Tubes on U.S. 41 (U.S. 76, SR-8):  The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes occurs normally on Wednesday and Thursday nights during the week with the 3rd Tuesday of the month.  Work hours are between 8 p.m.-6 a.m.  Tunnels will be closed during cleaning, and detours will be marked accordingly as each tunnel is cleaned.  Contract completion date is June 2017.  [Diamond Specialized, Inc./Micka/CNQ174]


Happenings
Vintage Base Ball Opening Day For Chattanooga Clubs Is April 6
Vintage Base Ball Opening Day For Chattanooga Clubs Is April 6
  • 3/28/2024

The Lightfoot Club of Chattanooga and the Mountain City Club of Chattanooga will begin the 2024 season of vintage base ball (yep, two words) on the historic 6th Calvary polo field (6 Barnhardt ... more

4 Bridges Arts Festival Returns April 20-21
  • 3/28/2024

The Association for Visual Arts will present the 24th Annual 4 Bridges Arts Festival at the First Horizon Pavilion on the southside of downtown Chattanooga this April. The festival will take ... more

Volunteers Needed for American Battlefield Trust Park Day
  • 3/28/2024

Chickamauga and Chattanooga National Military Park is seeking volunteers for American Battlefield Trust Park Day. Sign-up will begin at 9 a.m. on Saturday, April 6 at the intersection of Woodland ... more