Weekly Road Construction Report

  • Thursday, October 23, 2014

Here is the weekly road construction report for Hamilton County:

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Road/Boulevard):  Weather permitting, the contractor may have lane closures throughout the project area on weeknights to perform road work.  On Saturday from 7 a.m.-3 p.m. the contractor will have lane closures on U.S. 27 North throughout the entire project area to mill and pave.  This work is needed to ready the northbound side for a future traffic shift.  They will also be working on retaining walls and bridges throughout the project area.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is February. 

Construction of a State Industrial Access route serving Volkswagen Group of America, including grading, drainage and paving:  Work on this project continues.  The contractor is in the process of working on road and drainage, along with environmental measures.  Traffic will not be impacted at this time so no lane closures are needed.  Estimated project completion date is October.  

SR-148 resurfacing from  the Georgia State Line (LM 0.00) to U.S. 11 (U.S. 64, U.S. 72, SR-2) (LM 3.99); SR-318 resurfacing from U.S. 11 (U.S. 41, U.S. 64, U.S. 72, SR-2) (LM 0.00) to SR 148 (LM 1.05):  Work on this project continues.  The contractor will be working on the installation of guardrail, milling and paving operations.  The scheduled work hours are from 7 a.m.-7 p.m. Flaggers will assist with traffic control as needed.  Estimated completion date is November. 

Happenings
Weekly Road Construction Report
  • 4/19/2024

Here is the weekly road construction report for District 29: BRADLEY COUNTY I-75 at Paul Huff Parkway Interchange modifications: During this reporting period, the contractor will ... more

“GO LIVE” Summer Media Teen Camp Returns
“GO LIVE” Summer Media Teen Camp Returns
  • 4/19/2024

The City of Chattanooga’s Department of Community Development has partnered with Dynamo Studios to host the “GO LIVE” Summer Media Teen Camp, where participants can express their creativity and ... more

Crabtree Farms Plant Sale, Sculpture In The Sky Set This Weekend
  • 4/18/2024

Two annual springtime events will be taking place this weekend in Chattanooga. Crabtree Farms Plant Sale will be on Friday through Sunday from 9 a.m. until 3 p.m. each day. On Friday and Sunday, ... more