Weekly Road Construction Report

Thursday, August 02, 2012

Here is the weekly road construction report for Hamilton County:

I-24 resurfacing beginning at the Georgia State Line (LM 0.0/MM 171) to the bridge over Chattanooga Creek (LM 6.18/MM 177) including bridge deck repair: Paving and bridge repair work are complete.  The contractor will be addressing punchlist items at night between the hours of 9PM-6AM on Sundays through Thursdays.  One lane will remain open to traffic at all times.  THP will assist with traffic control.

Estimated project completion date is August 2012. 

 

U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  HAMILTON COUNTY, U.S. 27 (SR-29) reconstruction project from Manufacturers Road (Olgiati Bridge over the Tennessee River) to U.S. 127 (SR-8, Signal Mountain Boulevard):  Weather permitting, the contractor will have lane closures throughout the project area on weeknights to perform road work.  They will also be working on retaining walls and bridges throughout the project area.  The Manufacturers Road entrance ramp onto US-27 North has been closed until spring 2013 to allow for construction of several retaining walls and portions of the new bridges over the railroad and Manning Street.  Detours are posted.  The Manning Street and Whitehall Road exit ramps from U.S. 27 North have both been permanently closed.  During nighttime work, at least one lane will remain open in each direction.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is October 2014. 

 

College Drive East widening project from west of Sunkist Terrace to SR-317 (Apison Pike):  The contractor will be working on College Drive East throughout the project area placing barrier rail and installing erosion control items between 7AM- 6PM Monday through Saturday.  Flaggers will be in place to assist with traffic control.  Estimated project completion date is August 2012. 

 

Shallowford Road widening project from Gunbarrel Road to Jenkins Road, including grading drainage, and paving: The contractor will be laying pipe across the roadway at several locations.  This work will be performed during the day on weekdays only.  Flaggers will be in place to assist with traffic control.  Estimated project completion date is August 2013. 

 

SR-60 construction of concrete slab bridge over branch (LM 0.44): (This project is near the Meigs County Line.)  The contractor may be performing work throughout the project area between 7AM-6PM Monday through Saturday.  Flaggers will assist with traffic control.  Estimated project completion date is November 2012. 

 

Shallowford Road construction of concrete Bulb-Tee beam bridge over South Chickamauga Creek (LM 4.01), including grading drainage, and paving:  The contractor is constructing the new bridge and performing grading operations.  There will be no long-term lane closures as a result of this project.  Traffic has been shifted to Phase 1 of the new bridge while the original bridge is demolished and Phase 2 is completed.  The contractor may have intermittent short-term lane closures to perform bridge work during non-peak hours.  Flaggers will assist with traffic control as needed.  Estimated project completion date is August 2012. 

 

U.S. 11 (SR-2, Lee Highway) construction of a concrete box beam bridge over the CSX Railroad (LM 16.25), including grading, drainage and paving:  During this report period, there will be lane closures in each direction every day except Sunday to allow the contractor to place final paving and striping on the bridge.  At least one lane of traffic in each direction will be open at all times.  Flaggers will assist with traffic control as needed.  Estimated project completion date is August 2012. 

 

Daugherty Ferry Road construction of a concrete box beam bridge, including grading, drainage and paving, over Sale Creek (LM 0.79):  The project to replace the truss bridge over Sale Creek is underway, and the contractor has closed Daugherty Ferry Road to traffic at the bridge for the duration of the project.  The detour route using Coulterville Road and Elesea Road will be clearly marked.  Estimated project completion date is November 2012.

 

U.S. 127 (SR-8) resurfacing (thin mix overlay) from Miles Road (LM 18.87) to Sequatchie County Line (LM 23.16):  The contractor may implement temporary daytime lane closures and pace traffic at various times depending on the scope of work.  There will be no work done on this project during the World’s Longest Yard Sale.  Flaggers will assist with traffic control as needed.  Estimated project completion date is September 2012.  


Memorial Day Singing To Be Held At Patten Center

There will be a Memorial Day singing at the J. A. Patten Center in Lookout Valley Monday from 12-2 p.m.    There will be live music and family fun.  (click for more)

President Roosevelt’s Tree Army Presentations Are June 1-2

In celebration of 80th anniversary of the establishment of the Civilian Conservation Corps, Chickamauga and Chattanooga National Military Park invites the public to attend a weekend at the Chickamauga Battlefield Visitor Center on Saturday and Sunday, June 1-2.  The Great Depression caused stress and desperation among thousands of Americans as the economy fell apart, shattering ... (click for more)

Wade Hinton Named City Attorney

Wade Hinton, who led Mayor Andy Berke's transition team, has been chosen as city attorney. It is a joint appointment with the City Council, and the move was endorsed by a number of council members who appeared with the mayor at a press conference on Friday morning. Mayor Berke did not retain Mike McMahan, the longtime city attorney. He passed over Phil Noblett, a longtime ... (click for more)

Head Of BB&T's Chattanooga Commercial Banking Operations To Plead Guilty To Making Fraudulent Loans

The head of BB&T's Chattanooga commercial banking operations has been charged by federal authorities with making fraudulent loans. Tracy Brown is set to plead guilty to bank fraud on June 4. Authorities said Brown "appropriated the identities of three customers and took out fraudulent loans in their names. In October 2012, a customer of BB&T, D.M., went to the Ooltewah ... (click for more)

Immigration Reform - And Response

We do not have to pander to those in our country who were not invited and made their way here on their own. They are here against our laws that are already on the books which are not enforced.  They do not have negotiation rights to dictate to the United States government nor does our government have the right to pick and choose which laws are to be enforced or ignored so ... (click for more)

Roy Exum: So How Am I Really Doing?

I’ve gotten hundreds of jokes since Tuesday when I wrote about feeling a little puny lately and expressing my belief that laughter is the best medicine. After breaking some bones in my arm as I slept last week and having no idea there were already some other fractures, it looked pretty certain I had a case of “The Big C.” I’ve always felt that stands for “courage” but the medical ... (click for more)